  • The USCHO Fan Forum has migrated to a new plaform, xenForo. Most of the function of the forum should work in familiar ways. Please note that you can switch between light and dark modes by clicking on the gear icon in the upper right of the main menu bar. We are hoping that this new platform will prove to be faster and more reliable. Please feel free to explore its features.

MS Project Question

dxmnkd316

Lucia Apologist
Ok, I need help with MS Project. I have a rather large Gantt chart and I want to know if there's a way to make a task that is on the non-critical path as the project constraint. There are tasks that come after this but they aren't important and aren't required for the project to be considered complete to the customer.

A simplified view:
A---------->B---->C--->D
|
V
E-->F------>G

G is the start-up date and is what everyone but me would consider the project completion date. However, C & D are considered the critical path since they occur after G.

Any ideas?
 